Walls, Windows and What's Next: School Construction Updates

Walls, Windows and What's Next: School Construction Updates

Black Hawk & Gompers Construction Updates

What’s New?

Within the past two weeks, crews have moved downstairs and have started work on the lower-level interior walls.

Stud framing has finished in the southern lower-level classroom wing and masons have completed the block walls in the lower mechanical room. Mechanical, electrical and plumbing (MEP) crews are finalizing in-wall rough-ins on the upper level in preparation for door frame and pre-drywall inspections.

Enclosure progress continues as exterior framers continue along the north wall. Roofers have completed roofing over the gyms and are moving onto the last two roofs. Window frame installation has continued around the west and south sides of the building. Brick is expected to start next week in the south side of the building.

The Past Week

  • Interior framing starting in the lower-level
  • Exterior framing completed on upper and lower level of the new libraries
  • Interior masonry walls in the mechanical room
  • Roof blocking completed on upper and lower level of the new libraries

The Coming Weeks

  • Door frame and drywall install
  • Fireproofing in the commons and mechanical room
  • Interior masonry finishing in the new flex lab and music room
  • Window frame install around the elementary school entrance

Did You Know: This building features a layer of non-permeable and permeable air and vapor barrier (AVB) on walls with exterior metal panels. Non-permeable AVB blocks water vapor and air. Permeable AVB blocks air, but allows water vapor to move through the membrane. Air barriers are essential to keeping moisture out and preventing mold.

Sherman and Shabazz Construction Updates

What’s New?

Structural steel detailing and decking has been completed and Ironworkers will be transitioning to miscellaneous detailing behind interior masonry walls and preparing for stair installation. Concrete work continues throughout the building, with both slabs-on-grade and slabs-on-deck progressing. Most recently, Sherman Middle School classroom and offices were poured. Underground electrical and plumbing work continues ahead of upcoming concrete pours.

Cast stone and brickwork has begun on the Shabazz High School and is progressing south. Ahead of this exterior work the building envelope work continues to make steady progress. Exterior stud framing and sheathing are advancing along the east elevations of the Sherman Middle School. Weather barrier installation, including associated detailing and spray-applied work, follows the sheathing installation. Exterior insulated sheathing, roof blocking and window blocking are also progressing, followed by a final round of weather barrier detailing to complete the exterior wall assemblies prior to brick and metal panel work.

The Past Week

  • Installation of EPDM, a durable, rubber roofing material
  • Spray applied and painted on fireproofing
  • Fire protection pipe rough ins

Coming Up in Weeks Ahead

  • Interior mechanical, electrical and plumbing rough ins will begin next week
  • Electrical transformers will be set next week by MG&E
  • The final face of exterior framing will begin in two weeks

Did You Know: Before a single brick can be installed, crews must complete multiple layers of framing, sheathing, insulation, weather barriers and detailed flashing to help keep the building protected from Wisconsin's weather for decades.