2020 Referenda - Construction Phase
Exciting things are happening…
Thank you for your patience and cooperation as we begin construction from our 2020 Facilities Referendum. We understand construction can cause inconveniences in our building and communities. Updates on operational impacts and progress will be shared on this page and shared with each community as our construction journey continues creating Future Ready learning environments.
Have a Question about a Construction Project? Use the Let's Talk red tab on the bottom right corner of your browser or click here.
- Capital High School
- East High School
- La Follette High School
- Memorial High School
- Southside Elementary School
- West High School
Capital High School
Referendum Construction Renderings
Construction Updates
Spring is finally here and construction at Capital High School is inching closer to completion every day! Inside the building, classrooms and offices are starting to take shape.
We are committed to keeping you informed as we complete construction for the MMSD 2020 facilities referendum.
As we inch closer to spring, construction at Capital High School is making great progress.
Construction crews continue to make progress on the Capital High School renovations.
Construction work for the new Capital High School, formerly the Hoyt Elementary and Madison School and Community Recreation (MSCR) building, is well underway!
Construction work for the new Capital High School, formerly the Hoyt Elementary and Madison School and Community Recreation (MSCR) building, is well underway!
Tentative Construction Schedule
These projects have many detailed schedules such as abatement, permits, furniture, start-up and testing, etc. These dates are for general reference only and are subject to change.
Issued for Bid
11/3/2021
Bids Received
11/23/2021
Construction Begins
10/3/2022
Building Turnover - Normal Occupancy
8/11/2023
East High School
Construction Updates
We are committed to keeping you informed as we complete construction for the MMSD 2020 facilities referendum.
Over spring break, demolition was completed in the pool locker rooms and is ongoing in the next phase of classroom renovations including the second-floor career services and English rooms.
The current phase of lower-level locker room renovations is nearly complete, just in time for spring athletics to start up in the coming weeks.
We are committed to keeping you informed as we complete construction for the MMSD 2020 facilities referendum.
Find out about this East High School construction update provided by Findorff
Find out about this East High School construction update provided by Findorff
Find out about this East High School construction update provided by Findorff
Find out about this East High School construction update provided by Findorff
Find out about this East High School construction update provided by Findorff
Find out about this East High School construction update provided by Findorff
Find out about this East High School construction update provided by Findorff
Find out about this East High School construction update provided by Findorff
Find out about this East High School construction update provided by Findorff
Tentative Construction Schedule
These projects have many detailed schedules such as abatement, permits, furniture, start-up and testing, etc. These dates are for general reference only and are subject to change.
Issued for Bid
1/13/2022
Bids Received
2/8/2022
Construction Begins
5/2/2022
Building Turnover - Normal Occupancy
8/30/2024
La Follette High School
Construction Updates
We are committed to keeping you informed as we complete construction for the MMSD 2020 facilities referendum.
We are committed to keeping you informed as we complete construction for the MMSD 2020 facilities referendum.
We are committed to keeping you informed as we complete construction for the MMSD 2020 facilities referendum.
We are committed to keeping you informed as we complete construction for the MMSD 2020 facilities referendum.
Find out about this La Follette High School construction update provided by Findorff
Find out about this La Follette High School construction update provided by Findorff
Find out about this La Follette High School construction update provided by Findorff
Find out about this La Follette High School construction update provided by Findorff
Find out about this La Follette High School construction update provided by Findorff
Find out about this La Follette High School construction update provided by Findorff
Find out about this La Follette High School construction update provided by Findorff
Find out about this La Follette High School construction update provided by Findorff
Find out about this La Follette High School construction update provided by Findorff
Tentative Construction Schedule
These projects have many detailed schedules such as abatement, permits, furniture, start-up and testing, etc. These dates are for general reference only and are subject to change.
Issued for Bid
11/30/2021
Bids Received
12/21/2021
Construction Begins
6/1/2022
Building Turnover - Normal Occupancy
8/30/2024
Memorial High School
Construction Updates
As the school year heads toward its completion, so do the areas under construction in Phase 3 of Memorial High School’s renovations.
We are committed to keeping you informed as we complete construction for the MMSD 2020 facilities referendum.
The arts and technical education remodel and additions are nearly ready for students and staff.
Two more areas of construction are now complete – the new band, choir, orchestra, and practice rooms, and a group of renovated locker rooms and bathrooms south of the fieldhouse.
Find out about this Memorial High School construction update provided by Findorff
Find out about this Memorial High School construction update provided by Findorff
Find out about this Memorial High School construction update provided by Findorff
Find out about this Memorial High School construction update provided by Findorff
Find out about this Memorial High School construction update provided by Findorff
Find out about this Memorial High School construction update provided by Findorff
Find out about this Memorial High School construction update provided by Findorff
Find out about this Memorial High School construction update provided by Findorff
Find out about this Memorial High School construction update provided by Findorff
Tentative Construction Schedule
These projects have many detailed schedules such as abatement, permits, furniture, start-up and testing, etc. These dates are for general reference only and are subject to change.
Issued for Bid
2/3/2022
Bids Received
3/1/2022
Construction Begins
5/2/2022
Building Turnover - Normal Occupancy
8/30/2024
Southside Elementary School
Construction Updates
We are committed to keeping you informed as we complete construction for the MMSD 2020 facilities referendum.
We are committed to keeping you informed as we complete construction for the MMSD 2020 facilities referendum.
We are committed to keeping you informed as we complete construction for the MMSD 2020 facilities referendum.
Mother nature gave us a few good weeks that allowed a large section of the main roof to be installed and the interior trades to ramp up.
Find out about this Southside Elementary School construction update provided by Findorff
Find out about this Southside Elementary School construction update provided by Findorff
Find out about this Southside Elementary School construction update provided by Findorff
Find out about this Southside Elementary School construction update provided by Findorff
Find out about this Southside Elementary School construction update provided by Findorff
Find out about this Southside Elementary School construction update provided by Findorff
Find out about this Southside Elementary School construction update provided by Findorff
Find out about this Southside Elementary School construction update provided by Findorff
Tentative Construction Schedule
These projects have many detailed schedules such as abatement, permits, furniture, start-up and testing, etc. These dates are for general reference only and are subject to change.
Issued for Bid
2/24/2022
Bids Received
3/22/2022
Construction Begins
6/4/2022
Building Turnover - Normal Occupancy
8/4/2023
Referendum Construction Rendering
West High School
Construction Updates
We are committed to keeping you informed as we complete construction for the MMSD 2020 facilities referendum.
We are committed to keeping you informed as we complete construction for the MMSD 2020 facilities referendum.
We are committed to keeping you informed as we complete construction for the MMSD 2020 facilities referendum.
Find out about this West High School construction update provided by Findorff
Find out about this West High School construction update provided by Findorff
Find out about this West High School construction update provided by Findorff
Find out about this West High School construction update provided by Findorff
Find out about this West High School construction update provided by Findorff
Find out about this West High School construction update provided by Findorff
Find out about this West High School construction update provided by Findorff
Find out about this West High School construction update provided by Findorff
Find out about this West High School construction update provided by Findorff
Tentative Construction Schedule
These projects have many detailed schedules such as abatement, permits, furniture, start-up and testing, etc. These dates are for general reference only and are subject to change.
Issued for Bid
12/30/2021
Bids Received
1/25/2022
Construction Begins
5/2/2022
Building Turnover - Normal Occupancy
8/26/2024