Mother nature cannot stop construction progress at Southside Elementary School

Mother nature cannot stop construction progress at Southside Elementary School
We are committed to keeping you informed as we complete construction from the MMSD 2020 facilities referendum.

Mother nature cannot stop construction progress at Southside Elementary School

Construction continues at Southside Elementary School despite the winter weather. On the exterior of the building, workers are framing the north side, installing the air/vapor barrier on the west side, and putting in the window frames on the south and west sides. Roofing work continues to push on as weather permits and temporary heating on the interior is allowing work to progress on schedule. Wall framing is nearly complete on the third floor and about 30 percent complete on the second floor. In addition, ductwork, plumbing piping, sprinkler piping, and electrical work are ongoing throughout the building.
Workers have started framing the skylight for the exterior roof garden and commons areas

Workers have started framing the skylight for the exterior roof garden and commons areas

 

Ongoing construction activities

  • Continuing work on the northwest section of the building with exterior framing, sheathing, and the air/vapor barrier
  • Installing roofing on the south portion of the building
  • Putting in window frames on west side
  • Installing interior metal stud partitions on the second floor
  • Starting in-wall mechanical, electrical, and plumbing work on the third floor
  • Continuing main ductwork, piping, and electrical work on all floors
Window frames have been installed on the south side of the building
Window frames have been installed on the south side of the building
 

For additional information or questions, visit the MMSD construction page.

Did you know?

Currently, there are 11 different skilled trades working at Southside Elementary School, including laborers, carpenters, roofers, waterproofers, glazers, ironworkers, insulators, plumbers, electricians, sheet metal workers, and pipefitters. On average, there are between 45-50 tradespeople working on site, which will nearly double as the project moves further along.

Interior wall framing continues on the second floor

Interior wall framing continues on the second floor

Plumbing work in the third-floor bathrooms has started

Plumbing work in the third-floor bathrooms has started

 
The view from the northwest shows significant progress on the building structure since last month

The view from the northwest shows significant progress on the building structure since last month