Skip To Main Content

Select a School

Madison Metropolitan School District

Construction is progressing on Southside Elementary School

Construction is progressing on Southside Elementary School
We are committed to keeping you informed as we complete construction from the MMSD 2020 facilities referendum.

Construction is progressing on Southside Elementary School

Construction activity is moving along quickly at the Badger Rock site as crews are making progress on the new Southside Elementary School.

Work continues for concrete footings and foundations on the north side of the site. Construction crews are pouring the concrete footings several days a week, with foundation wall pours happening almost as frequently. The underground plumbing and electric piping is complete on the south side of the project site. Crews will soon start pouring the first section of the concrete foundation slab.

Site is prepped with a vapor barrier prior to pouring the first section of the concrete foundation

The site is prepped with a vapor barrier prior to pouring the first section of the concrete foundation slab

 

Upcoming construction activities

  • Continuing work on the concrete footings and foundation on the north side

  • Pouring the first section of the concrete foundation slab

  • Beginning work on the masonry firewall, which will provide a fire separation between the existing building and the new structure

  • Starting structural steel work for the south end of the building in the upcoming weeks

work is progressing as the underground utilities, vapor barrier, and concrete reinforcing installed

On the south side of the building, work is progressing as the underground utilities, vapor barrier, and concrete reinforcing wire are installed

 

For additional information or questions, visit the MMSD construction page.

Did you know?

A plastic yellow vapor barrier is placed on the site in preparation for the concrete foundation slab to be poured. This vapor barrier helps prevent moisture from entering the concrete foundation, allowing it to properly cure and stay dry.

Crews are forming the foundation walls for the west stair tower

Crews are forming the foundation walls for the west stair tower

Work is ongoing for the concrete footings on the northwest corner of the site

Work is ongoing for the concrete footings on the northwest corner of the site

 
south side of the site was prepped and leveled in preparation for the concrete foundation pour

The south side of the site was prepped and leveled in preparation for the concrete foundation pour