Skip To Main Content

Select a School

Madison Metropolitan School District

Capital High construction forges on

Capital High construction forges on

Construction crews continue to make progress on the Capital High School renovations. Inside the building, wall and door frames are beginning to showcase the building’s new layout. Following closely behind, mechanical, electrical, plumbing, and fire protection (MEPF) work is
starting. MEPF contractors are installing new systems throughout the building, including boilers and air handling units (AHUs). Several concrete pours have covered new underground plumbing work in the lower and top levels of the building.

On the exterior, the new elevator shaft has been completed. The exterior chiller pad concrete was poured and is ready for the new equipment to be installed.

Upcoming work:

  • Continuing interior wall and door framing, with MEPF work following closely behind
  • Installing window and roof blocking, which will provide support for the windows and roof installation later this spring
  • Continuing drywall and taping on the lower levels
  • Finishing remaining masonry and exterior framing work

DID YOU KNOW? Hoyt Community Park, which neighbors the new Capital High School building, was formerly a sandstone and dolomite quarry in the 1890s that provided resources for the construction of several historical buildings and street pavements throughout Madison. To align with the existing building façade and the natural park environment, the addition at Capital High School will complement the look of the wood siding on the exterior of the building.

 

northern exterior of the building

The new elevator addition can be seen on the northern exterior of the building.

 

Interior wall frames are being installed

Interior wall frames are being installed and door frames are being set throughout all three levels of the school.

 

The new AHU was installed in the mechanical room

The new AHU was installed in the mechanical room.

 

Concrete was poured over the underground plumbing

Concrete was poured over the underground plumbing in the future culinary space.

 

The exterior concrete chiller pad was poured

The exterior concrete chiller pad was poured in preparation for the new equipment that is coming soon