Summer is here and Capital High School is making great progress both inside and out! Flooring is being laid in all the classrooms and the hallway floors are complete. Bathroom accessories are being installed and the last ceramic tile finishes are going in. Data cabling is being pulled throughout the building and lights are being powered up. The culinary space equipment is starting to be installed and the new gym equipment is going up!
Outside, site work is progressing well. The new storm lines in front of the school are underway which will greatly improve drainage. New sidewalks and curbs will be poured following the storm line install.
Upcoming construction activities
- Placing new gym floor
- Dropping ceiling tiles throughout building
- Paintingwoodtrimandlockers
- Starting sidewalk work on Regent Street
- Continuingexteriorfinishesonelevatoraddition
- Preparing for the elevator installation
DID YOU KNOW? The culinary space will feature a teaching station with the more industrial equipment and four student stations. There will also be two monitors above the teaching station with a camera that will show students what the teacher is doing live.