Starting the final phase of construction

Starting the final phase of construction

The mechanical, electrical, plumbing, and fire protection (MEPF) work is nearly complete at East High School. Next, the focus will shift to the final phase of the construction project, which includes painting, installing ceilings, lighting, and other finishes.

Now that students are on summer vacation, construction work is in full swing throughout the building. Crews recently completed the practice field and the concrete floor for the woodshop mezzanine. Work on the woodshop mezzanine was challenging because ironworkers had to fabricate a steel deck strong enough to support the concrete floor, and then crews had to pour the concrete on an elevated surface.

Updates on current and upcoming work

  • Installing the ceilings on the first and second floors
  • Starting landscaping around the building and in the courtyard
  • Installing new heating, ventilation, and air conditioning (HVAC) units to help regulate the temperature throughout the building

Did You Know? The new artificial turf on the athletic practice field at East High School is made up of approximately 640 million synthetic strands of rubber.

goal post at east high school

Turf installation and striping are now complete on the practice field

 

carpeted forum area

New carpeting was installed in the Forum, which creates a more comfortable space for students during the passing period

 

empty cafeteria with polished floors and colorful design on wall

Crews are polishing the concrete floor in the cafeteria, which is the last task to complete this space

 

room under construction

Workers are building a new wall between the computer lab and the woodshop

 

room with concrete floors under construction

The concrete floor for the mezzanine was poured, kicking off the start of the woodshop renovations