In the courtyard addition, the new cooling tower unit is being installed
Progress on the new additions
-
Constructing the exterior masonry walls for the new cafeteria and music area expansion
-
Continuing enclosure activities in the courtyard addition, including installing the exterior wall, roofing, and the new cooling tower unit
-
Starting to install two new elevators, with the elevator in the courtyard addition set to begin at the end of the month and the welcome center lobby elevator to follow
In recognition of Construction Inclusion Week, construction workers and project team members are participating in daily toolbox talks focused on fostering conversations and continuing to build awareness of the importance of inclusion in the construction industry
For additional information or questions, visit the MMSD construction page.
Did you know?
Before electric air conditioners existed, large blocks of ice were used to cool homes and businesses. The ice absorbed heat and slowly melted as it warmed up. The use of ‘tons’ to measure cooling capacity comes from this time. A ton refers to the amount of heat it takes to completely melt a ton of ice. The new cooling system being installed at East will have approximately 1,000 tons of cooling capacity, meaning the system installed is equivalent to 1,000 blocks of ice being placed around the school to offset the heat generated from air temperatures and occupants inside the building.
Exterior masonry walls are being constructed for the new cafeteria expansion
In the lower level, walls have been painted, the ceiling grid has been installed, and the remainder of the finishing touches will soon follow
MEPF work and framing have begun in the foreign language classrooms
The new elevators in the courtyard addition and main lobby are scheduled to be installed soon