Continuing Work on Building Renovations
In the science classrooms, concrete trenches were filled in and areas for new windows have been cut open
Making progress on the additions
-
Setting structural steel on the new gymnasium and weight room addition
-
Continuing framing and wall infills for the addition and infill of ‘The Pit’
-
Installing exterior vapor barrier and temporary weather barriers on the addition
-
Building masonry walls for the athletic addition
Structural steel is being set on the new gymnasium and weight room addition
For additional information or questions, visit the MMSD construction page.
Did you know?
Once the 2020 Facilities Referendum construction is complete, La Follette High School will have 18 additional windows throughout the renovated areas and 20 new windows in the building additions. These windows will provide additional, much-needed natural light throughout the school to support student and staff mood, alertness, concentration, and energy levels.
Framing and wall infills for the addition and infill of ‘The Pit’ is ongoing
Framing and MEPF work is well underway in the Library Media Center renovation