Exciting progress at La Follette
Outside the building, the turf crew is putting the finishing touches on the new turf field at Lussier Stadium. The track has been paved and bleachers are getting installed on the east end of the field. Meanwhile, the concrete foundations for the courtyard expansion were poured and are ready to be backfilled. When complete, the expanded corridors will improve building circulation.
The new concrete curb for the south parking lot and entrance has been poured
More finishes coming soon
-
Patching and priming walls in the coming weeks for new paint in classrooms
-
Hanging cement board on the bathroom walls in preparation for the new tile finish
-
Preparing to install new laboratory casework in the science and chemistry classrooms
-
Installing the elevator in the newly constructed elevator shaft
The bathroom walls were framed, and in-wall support blocking and drywall are being installed
For additional information or questions, visit the MMSD construction page.
Did you know?
Once complete, the freshly renovated Lussier Stadium will feature an expanded turf field, larger track, and new bleachers, lighting, and pole vault pit. The expanded layout will provide additional opportunities for students and the community to use the space. Lussier Stadium will be open and ready for the first home varsity football game in August 2022!
The concrete foundations for the courtyard expansion are ready to be backfilled, which improve building circulation when complete
Walls in the new classroom spaces are being framed
Crews made significant progress on Lussier Stadium with a new turf field, track, and bleachers