The Performing Arts Center (PAC) will be complete in about two weeks. The new seating and flooring were installed, and the space is coming together nicely. Mechanical, plumbing, and electrical work is complete in the technical education wing. The painters, carpenters, and glazers are now working on finishing items in this area.
Crews started the final phase of construction, which includes renovations to the old main entrance and the 10,000-square-foot space leading into the new café/commons area. Workers started mechanical, electrical, plumbing, and fire protection (MEPF) work in this area and will be installing drywall next.
Updates on current and upcoming work
- Installing stage curtains, rigging, flooring, and finishing painting in the PAC
- Sealing concrete and installing doors and hardware in the technical education wing
- Finishing MEPF work in the final phase of construction
Did You Know? In addition to a new stage, rigging system, and updated finishes, the newly renovated Performing Arts Center (PAC) is larger and now has seating for up to 548 people.
Seating was installed in the PAC
Crews are installing carpeting and painting the handrails in the PAC
The final phase of construction is underway
New glass along the hallway brings more natural light between the classrooms and the hallway
Crews are sealing the concrete in the technical education area and installing the flooring in the physical education classroom and fitness room