Summer construction is coming to a close
New casework has been installed in the science classrooms
What’s happening with the new corridor?
-
Installing steel structure for the new hallway connecting the commons with the academic wing, which is expected to be complete in December 2022
-
Finishing concrete work this week and starting exterior stud framing on the north end of the corridor
-
Installing temporary enclosures for student access to the academic wing until the new corridor is complete later this winter
Bathrooms have been completely remodeled with new tile, bathroom partitions, and fixtures
For additional information or questions, visit the MMSD construction page.
Did you know?
The open-air area underneath the existing second-floor Library Media Center is known as “The Pit.” As part of the 2020 Facilities Referendum, “The Pit” will be transformed into a well-lit instructional space providing experiential learning and improved accessibility. This renovated space will be complete in December 2022.
The new elevator is being installed, along with another opening allowing access from the corridor
Work on the new corridor is ongoing and will be complete in winter of 2022
Workers are putting the finishing touches on the classrooms for the upcoming school year