Wrapping Up the Fall Phase of Construction
Structural steel is set on the new gymnasium and weight room addition
Updates on current work
-
Completed structural steel on the new gymnasium and weight room addition
-
Installed a new boiler system in the mechanical room, which is up and running
-
Applied the spray-on exterior vapor barrier and installed temporary weather barriers
-
Started planning and preparing for the next phase of construction in the life skills department
The new boiler system was installed in the mechanical room
For additional information or questions, visit the MMSD construction page.
Did you know?
Starting at the end of December, the next phase of construction will focus on renovating the life skills department, which will include upgrades to spaces for specialty classes such as kitchen and life skills, interior and fashion design, and health sciences.
The casework and ceiling grid was installed in the science wing renovation
The first coat of paint is being applied in ‘The Pit’ infill
The spray-on exterior vapor barrier has been applied to the new addition