Skip To Main Content

Select a School

Madison Metropolitan School District

Additions at Memorial Are Taking Shape

Additions at Memorial Are Taking Shape
We are committed to keeping you informed as we complete construction from the MMSD 2020 facilities referendum.

Additions at Memorial are taking shape

The additions at Memorial High School are continuing to take shape as the structural work is nearing completion and weather barriers on the walls and roof are being installed. Construction crews started framing interior walls in the music addition. In the next few weeks, workers will pour the concrete slab for the northern technical education and science, technology, engineering, and math (STEM) addition.
 
Inside the existing building, wall framing and drywall work on the second floor math and science classrooms are complete. Next up in these areas, workers will start drywall finishing and painting. Light fixtures and flooring will be installed as we near the completion of these spaces around the semester break. In the locker rooms, walls are built and mechanical work is well underway. These areas are expected to be completed in mid-February 2023.
wall framing, in-wall support blocking, plumbing, and electrical work are complete

On the second floor, wall framing, in-wall support blocking, plumbing, and electrical work are complete in the future lab and science classrooms

 

Upcoming construction activity

  • Starting to paint and install lighting and ceilings in the math and science classrooms on the second floor

  • Beginning mechanical, plumbing, and electrical work in the locker rooms south of the fieldhouse

  • Installing drywall and windows in the music addition

  • Completing the roof on the music addition

  • Wrapping up the structural steel work on the technical education addition, followed by exterior wall framing

Setting steel for the wall and roof structure on the technical education and STEM addition

Ironworkers are setting steel for the wall and roof structure on the technical education and STEM addition on the east side of the school

 

For additional information or questions, visit the MMSD construction page.

Did you know?

Most of the concrete foundation work for the project is now complete. As of early October, 665 cubic yards of concrete have been poured at Memorial High School. This is about 70 trucks worth, almost enough to fill the high school’s pool! A vast majority of this concrete is below the ground and makes up the foundations of the new technical education and music additions.

walls & ceilings have been painted, and mechanical, electrical, and piping mains are being installed

In the renovated technical education areas, walls and ceilings have been painted, and mechanical, electrical, and piping mains are being installed

locker rooms south of the fieldhouse, new block walls are nearly complete

In the locker rooms south of the fieldhouse, new block walls are nearly complete, to be followed by paint, ceilings, and flooring finishes

 
steel installation is ongoing to the north, while concrete & masonry walls and underground plumbing

In the technical education addition, steel installation is ongoing to the north, while concrete and masonry walls and underground plumbing are being completed to the south