Construction continues as the summer rush begins

Construction continues as the summer rush begins

With school out for the summer, construction crews are actively working throughout the building. In the technology education space, mechanical, electrical, plumbing, and fire protection (MEPF) systems have been installed. This area will receive fresh paint and a new flooring finish in the coming weeks.

The first- and second-floor bathroom renovations are also progressing on schedule. Crews finished framing, drywall, and painting, and are now installing ceramic tile.

On the exterior, work continues on the future turf athletic field. The field goal and netting posts were installed. Fine grading begins in the coming weeks, and the turf will be installed.

Upcoming construction activity

  • Continuing site work and grading for the future turf field
  • Finishing the flooring in the first-floor classrooms
  • Grading the practice field site near the tennis courts
  • Installing ceramic tile and plumbing fixtures in the first and second-floor bathrooms
  • Installing remaining flooring and ceilings in the hallways throughout the building

Did You Know? The wood shop received an upgraded duct collector system, which involved the removal of the old, aging system. The new system contains two 55-gallon drums for cyclone filters and one 55-gallon drum for a shaker filter – a combined 165 gallons of space for the dust and debris to be filtered into and stored safely!

New paint and ceilings were installed in the first-floor bathrooms

New paint and ceilings were installed in the first-floor bathrooms

 

The new dust collector system was installed on the roof of the woods shop

The new dust collector system was installed on the roof of the woods shop

 

New tile was installed in the second-floor bathrooms and plumbing fixtures will be installed soon

New tile was installed in the second-floor bathrooms and plumbing fixtures will be installed soon

 

The first-floor classrooms received a fresh coat of paint and a new ceiling

The first-floor classrooms received a fresh coat of paint and a new ceiling

 

Casework was installed in the first-floor classrooms

Casework was installed in the first-floor classrooms