Skip To Main Content

Select a School

Madison Metropolitan School District

Construction progress on the building additions

Construction progress on the building additions
We are committed to keeping you informed as we complete construction from the MMSD 2020 facilities referendum.

Construction progress on the building additions

Although the weather is getting colder, that hasn’t stopped construction at West High School from continuing to make great progress. There are currently three large cranes onsite, all being used for different parts of the construction project.
  • A 90-ton crane is setting the steel in place for the new pool area.

  • A 200-ton crane is moving masonry materials to the new gym space.

  • A 250-ton crane is setting the steel in the courtyard by transporting steel bundles over the building.

Steel structure is complete, which will eventually be a new corridor from the auditor

The steel structure for the interior courtyard addition is complete, which will eventually be a new corridor from the auditorium to Stevens gym

 

Wrapping up the interior phase of work

This week marked the completion of the first-floor locker rooms and the third-floor science classroom renovations. As construction crews are wrapping up other outstanding items on the interior, school staff will begin to move into the newly completed spaces. Next, workers will start building new temporary walls to separate spaces for the next phase of construction, which includes renovations to additional classrooms and office spaces in the south portion of the third floor.

Locker rooms are complete on the first floor below Stevens gym

Locker rooms are complete on the first floor below Stevens gym

 

For additional information or questions, visit the MMSD construction page.

Did you know?

The size (also called tonnage) of a crane needed to complete a task is based on specific calculations that define its tonnage rating. A crane’s tonnage rating is determined by how much weight it can pick up and how high materials will be lifted. At West High School, the three cranes onsite have varying tonnage ratings that support different jobs on the construction site.

Masons have started installing concrete masonry unit (CMU) block walls on the new gym space

Masons have started installing concrete masonry unit (CMU) block walls on the new gym space

four new ADA-accessible restrooms and shower rooms in the new locker room spaces are complete

The four new ADA-accessible restrooms and shower rooms in the new locker room spaces are complete

 
Operators use a 250-ton crane to set the steel in place for the new courtyard addition

Operators use a 250-ton crane to set the steel in place for the new courtyard addition