Crews have been working hard to wrap up interior renovations throughout West High School for staff to begin moving into these spaces.
On the exterior, the turf athletic field is complete. Work is wrapping up on the practice fields, including pouring the asphalt base for the track and seeding the grass. In the next week, crews will lay the track surface and add striping.
Work on the interior courtyard is well underway. The storm sewer replacement is complete, and utility crews are doing some final utility work in this area. Next week, workers will finish the site work with asphalt paving and curbs.
Upcoming construction activity
- Wrapping up final remaining interior work items for staff to begin moving in
- Laying the track surface and finishing seeding on the practice field
- Pouring the asphalt pavement in the interior courtyard and parking area
- Pouring the final layer of asphalt in the Van Hise parking lot
Did You Know? The new practice fields at West High School include two full length fields, a sprint track, discus, shot put, long jump, high jump, and pole vault.