Construction crews continue to make significant progress on the new pool and gym addition. The final concrete pour of the pool body was completed this week and crews will work to backfill around the perimeter. Outside, the roofers have finished above the addition and will now move to the lower roofs. Also, the masonry has begun and will continue with pre-cast concrete and brick finish.
Crews continue installing air and vapor barrier on the exterior of the building over the concrete blocks. Window installation has also begun and will help enclose the building to begin painting and drywall activities.
Renovations continuing across the school
- Began demolition and environmental work in the second-floor classrooms and library
- Completed third-floor classroom renovations
- Continued installing mechanical, electric, plumbing, and fire (MEPF) finishes and final paint in the third-floor music area
- Started work on the new welcome center, with crews pouring the concrete footings and foundation
DID YOU KNOW? Once complete, the renovated second-floor history classrooms and library will have new flooring, wall finishes, light fixtures, plumbing, and heating, ventilation, and air conditioning (HVAC) throughout these spaces. These renovated areas are slated to be complete by the end of July