Out with the old, in with the new!

Out with the old, in with the new!

The newly renovated theater is nearly complete. Workers finished installing new seating, wall coverings, carpeting, ceiling, and lighting. Work on the stage is also wrapping up, which includes final electrical wiring and installing the curtains. In addition, new flooring is being installed in the corridors surrounding the theater.

On the first floor, crews started demolition in the classrooms. Concrete has been poured and new walls have been framed in the bathrooms. Once the mechanical, electrical, plumbing, and fire protection (MEPF) work is complete, workers will begin installing drywall and taping.

The new elevator that provides access to the fourth-floor classrooms is nearly complete. Crews wrapped up the exterior brickwork in that area and removed the scaffolding.

Upcoming construction activity

  • Cleaning and putting the finishing touches on the theater
  • Wrapping up demolition activities in the first-floor classrooms
  • Framing, taping, and painting the walls on the first floor
  • Installing the elevator and lobby finishes

DID YOU KNOW? In the newly remodeled theater, the old seats were removed and replaced with new seats. Over the past few weeks, crews installed roughly 600 seats on the main floor with another 300 on the balcony. This space now has enough seats to host the 2024 West High School graduating class, with seats left over!

empty theater seats at West High School

In the theater, seats have been installed and final cleaning has started

empty hallway under construction

Flooring is being installed in the second-floor corridor connecting the athletics and theater spaces

room under construction with two doorways

Crews finished painting and installing doors in third-floor biology offices and flooring will be installed this week

room with wall framing and MEPF installation

Wall framing and MEPF installation continues in the first-floor bathrooms

Empty classroom with windows under construction

The fourth-floor collaborative space is nearly complete

theater with stage in front of the room

Crews started framing the theater control booth this week