Skip To Main Content

Select a School

Madison Metropolitan School District

The final phase of classroom renovations has begun!

The final phase of classroom renovations has begun!

With the previous first-floor classroom renovations now complete, crews have shifted focus to the classrooms by the athletic and technical education wing. Demolition of the walls and flooring is complete, and workers are constructing the new concrete masonry unit (CMU) walls.

Steel beams have been installed and reinforced in the first- and second-floor bathrooms by the technical education and athletics spaces. Next, workers will install the mechanical, electrical, plumbing, and fire protection (MEPF) infrastructure.

New lighting has been installed in the auto shop, and the plumbers are installing a new in-floor drain system. Site work continues on the future athletic field with site grading and infilling the retaining wall.

Upcoming construction activity

  • Installing MEPF infrastructure and wall frames in the first- and second-floor bathrooms
  • Continuing plumbing and concrete work in the auto shop
  • Continuing site and utility work on the future athletic field

DID YOU KNOW? Masons will be installing special connectors, called FERO Break-Away Fire-Release Connectors, between the existing building and the new athletics addition. These connectors are meant to maintain the structural integrity of the wall while minimizing damage in the event of a fire. Break-away connectors are typically used when constructing a new addition that is attached to an existing building.

First floor athletic and technical education classroom under construction

Progress in the first-floor athletic and technical education classrooms

 

A field under construction at West High School

Crews started site work on the turf practice field this week

 

Auto shop floor under construction

The in-floor drain has been installed in the auto shop and concrete will be poured back into the trench

 

Bathroom under construction with first floor beams reinforced

In the first-floor bathrooms, the steel beams have been reinforced and MEPF infrastructure is being installed

 

Cinder blocks stacked in technical education room that is currently under construction

CMU walls are being constructed in the first-floor technical education classrooms

 

Engineering classroom with floors under construction

Crews removed the existing flooring in the engineering classroom to prepare for the new finishes