Wrapping up classroom renovation work

Wrapping up classroom renovation work

The first-floor classroom renovations are nearly complete. The mechanical, electrical, plumbing, and fire protection (MEPF) systems have been upgraded, and these spaces received a fresh coat of paint and updated finishes. Next week, bathroom finishes and accessories will be installed.

Construction crews are shifting focus to the first-floor bathroom renovations near the technical education area and the second-floor bathrooms near Stevens Gym. Demolition is wrapping up in those spaces, and the framing and concrete work will begin shortly. In the coming weeks, MEPF work will also begin.This week, site work for the new athletic field started. Crews are prepping the area for storm and electrical utility installation.

Upcoming construction activity

  • Beginning demolition in the athletic and technical education classrooms
  • Doing plumbing, concrete, and steel work in the first-floor technical education and athletic wing bathrooms
  • Continuing grading and site work for the future turf practice field 

Did You Know? In the current phase of first-floor renovations, there are approximately 2,426 square feet of new vinyl composite flooring (VCT) in the hallway. Throughout the entire school building, there are approximately 33,554 square feet of new VCT flooring in the hallways. If each flooring tile was placed in a straight line, it would be approximately 6.35 miles long. To put this in perspective, the line of tile would almost cover the entire distance from West High School to the Dane County Regional Airport!

A hallway partially completed with plumbing for water fountains

New flooring and tile around the drinking fountain are being installed in the first-floor hallway

 

Freshly painted classroom with wood floors installed

This first-floor classroom is ready for the carpet and base to be installed

 

Bathroom under construction with plumbing installed and tile layed.

In the first-floor bathrooms, plumbing fixtures and bathroom accessories will be installed this week, and tile will be complete next week

 

A room under construction with exposed beams and construction material

Demolition work continues in the first- and second-floor technical education bathrooms

 

A field under construction at West High School

Crews started site work on the turf practice field this week